Infrasafe Plays Key Role in £104m Nexus Metro Flow Track Dualling Project

Dec 3, 2022

The completion of the Nexus Metro Flow Project. This key project saw 3 sections of single track – pinch points on the Metro network – dualled during the12-week Major Line Closure between Pelaw and South Shields.

Infrasafe played an integral role in the supply of track supervision staff and support for this £104m track dualling project.

The Metro Flow project in numbers:

  • 4.6km of new rail
  • 8,450 new sleepers
  • 27,100 tonnes of new track ballast
  • 138 new overhead line masts

Now completed it will improve reliability across the whole of Metro and allow Nexus to increase the frequency of trains in the future.